Civic

community hospital
of the monterey peninsula

Project Description:  290,000 square foot addition and renovation to an existing 350,000 medical center.

Solution Caveats:  25% return on investment, significant emissions reduction, noise limitation on 17 mile drive.

Alternatives Considered:  Electric Photovoltaic Panels, Natural Gas Engine Cogeneration, Natural Gas Engine Driven Chillers, Bloom Energy Fuel Cell.

Solution Chosen:  1125KW Natural Gas Cogeneration System, New lighting using high efficiency fluorescent and LED sources.

Project Results:  25% return on investment, 28% reduction on facilities overall carbon foot print (1000 tons / year) and a 50% reduction of NO(2.9 tons / year).

BASEnergy Solutions